NPSAT1 Integrated Master Schedule (IMS)

Launch   0.00 12/7/09 12/7/09
Encapsulation   1.00 11/27/09 11/27/09
Integration onto LV   10.00 11/6/09 11/19/09
Launch Readiness Review   1.00 11/2/09 11/2/09
NPSAT1 Standalone Processing   5.00 10/26/09 10/30/09
SV Ship for Integration   5.00 10/19/09 10/23/09
System-Level Testing   30.00 11/21/08 1/1/09
Sytem-Level EMI/EMC   20.00 10/24/08 11/20/08
System Functional Test   20.00 9/26/08 10/23/08
Final Assembly   15.00 9/5/08 9/25/08
Final FLATSAT Verification   10.00 8/22/08 9/4/08
Harness Test (off-site)   10.00 8/8/08 8/21/08
Subsystem TVAC   20.00 7/11/08 8/7/08
Subsystem Vibration   20.00 6/13/08 7/10/08
Integrated Dev. Test   46.00 12/14/07 2/18/08
  Repeat of EIT (harness test) 0.00 12/14/07 12/14/07
  EIT-2: C&DH proc. & EPS Test 0.00 2/1/08 2/1/08
  EIT-3: C&DH proc., EPS, Battery 0.00 2/18/08 2/18/08
  C&DH proc., EPS, Battery, switchable loads Test 10.00 1/14/08 1/25/08
  Solar power (orbital) simulator setup 10.00 1/28/08 2/8/08
80C196_Sched.fts   253.00 5/7/07 4/23/08
  Test EPS Analog Board REV0 63.00 5/7/07 8/1/07
  Shunt Circuit Build/Test 1.00 12/5/07 12/5/07
  EPS Analog Board (Rev 1) - 1 brd 18.00 12/10/07 1/2/08
  Design ACS Analog Board 35.00 5/18/07 7/5/07
  Layout ACS analog board 35.00 6/15/07 8/2/07
  Flight ACS analog board 20.00 12/17/07 1/11/08
  Build ACS flight boards 19.00 1/14/08 2/7/08
  Prep for testing 56.00 11/28/07 2/13/08
  Functional test after vib. 2.00 2/14/08 2/15/08
  Flight processor board 33.00 11/26/07 1/9/08
  Flight Processor Boards (3) 13.00 4/7/08 4/23/08
  Test SMS analog board 43.00 11/7/07 1/4/08
  Flight Analog SMS Boards 58.00 1/2/08 3/21/08
Li-ionFlightBuild.fts   38.00 7/13/09 9/2/09
FlightMEMS.fts   28.00 7/21/08 8/27/08
SoftwareDevTest.fts   251.00 11/29/07 11/13/08
  EPS Software 10.00 1/10/08 1/23/08
  SMS Software 7.00 12/11/07 12/19/07
  ACS Software 22.00 11/29/07 12/28/07
  VISIM Software 11.00 9/1/08 9/15/08
  C&DH Software 117.00 11/29/07 5/9/08
  IDT Software 10.00 11/29/07 12/12/07
  Ground Station Software 68.00 2/11/08 5/14/08
  Ground Processing Software 49.00 9/8/08 11/13/08
CDH_Sched.fts   97.00 12/6/07 4/18/08
  Processor Board Software 17.00 12/10/07 1/1/08
  Mass Storage, A/D  25.00 1/2/08 2/5/08
  Power/Modem 44.00 12/17/07 2/14/08
  Flight CFTP Board 5.00 12/17/07 12/21/07
  GPS Interface 4.00 12/19/07 12/24/07
  RF System 86.00 12/6/07 4/3/08
  Integrate C&DH Box 10.00 3/5/08 3/18/08
  Conformal coat 10.00 2/15/08 2/28/08
  C&DH Standalone EMI/EMC 10.00 3/19/08 4/1/08
  SV Coaxial cabling design 11.00 4/4/08 4/18/08
GroundStation.fts   239.00 4/10/07 3/7/08
  Ground Station RF Hardware 237.00 4/10/07 3/5/08
  Ground Station Software 10.00 2/11/08 2/22/08
  End-to-End test 10.00 2/25/08 3/7/08
StrucMech.fts   227.00 12/5/07 10/16/08
  Flight Structure Final Mods 78.00 12/5/07 3/21/08
  Support / GSE Parts 227.00 12/5/07 10/16/08
  Mechanical Component Test 20.00 1/2/08 1/29/08