| Launch | 0.00 | 12/7/09 | 12/7/09 | |
| Encapsulation | 1.00 | 11/27/09 | 11/27/09 | |
| Integration onto LV | 10.00 | 11/6/09 | 11/19/09 | |
| Launch Readiness Review | 1.00 | 11/2/09 | 11/2/09 | |
| NPSAT1 Standalone Processing | 5.00 | 10/26/09 | 10/30/09 | |
| SV Ship for Integration | 5.00 | 10/19/09 | 10/23/09 | |
| System-Level Testing | 30.00 | 11/21/08 | 1/1/09 | |
| Sytem-Level EMI/EMC | 20.00 | 10/24/08 | 11/20/08 | |
| System Functional Test | 20.00 | 9/26/08 | 10/23/08 | |
| Final Assembly | 15.00 | 9/5/08 | 9/25/08 | |
| Final FLATSAT Verification | 10.00 | 8/22/08 | 9/4/08 | |
| Harness Test (off-site) | 10.00 | 8/8/08 | 8/21/08 | |
| Subsystem TVAC | 20.00 | 7/11/08 | 8/7/08 | |
| Subsystem Vibration | 20.00 | 6/13/08 | 7/10/08 | |
| Integrated Dev. Test | 46.00 | 12/14/07 | 2/18/08 | |
| Repeat of EIT (harness test) | 0.00 | 12/14/07 | 12/14/07 | |
| EIT-2: C&DH proc. & EPS Test | 0.00 | 2/1/08 | 2/1/08 | |
| EIT-3: C&DH proc., EPS, Battery | 0.00 | 2/18/08 | 2/18/08 | |
| C&DH proc., EPS, Battery, switchable loads Test | 10.00 | 1/14/08 | 1/25/08 | |
| Solar power (orbital) simulator setup | 10.00 | 1/28/08 | 2/8/08 | |
| 80C196_Sched.fts | 253.00 | 5/7/07 | 4/23/08 | |
| Test EPS Analog Board REV0 | 63.00 | 5/7/07 | 8/1/07 | |
| Shunt Circuit Build/Test | 1.00 | 12/5/07 | 12/5/07 | |
| EPS Analog Board (Rev 1) - 1 brd | 18.00 | 12/10/07 | 1/2/08 | |
| Design ACS Analog Board | 35.00 | 5/18/07 | 7/5/07 | |
| Layout ACS analog board | 35.00 | 6/15/07 | 8/2/07 | |
| Flight ACS analog board | 20.00 | 12/17/07 | 1/11/08 | |
| Build ACS flight boards | 19.00 | 1/14/08 | 2/7/08 | |
| Prep for testing | 56.00 | 11/28/07 | 2/13/08 | |
| Functional test after vib. | 2.00 | 2/14/08 | 2/15/08 | |
| Flight processor board | 33.00 | 11/26/07 | 1/9/08 | |
| Flight Processor Boards (3) | 13.00 | 4/7/08 | 4/23/08 | |
| Test SMS analog board | 43.00 | 11/7/07 | 1/4/08 | |
| Flight Analog SMS Boards | 58.00 | 1/2/08 | 3/21/08 | |
| Li-ionFlightBuild.fts | 38.00 | 7/13/09 | 9/2/09 | |
| FlightMEMS.fts | 28.00 | 7/21/08 | 8/27/08 | |
| SoftwareDevTest.fts | 251.00 | 11/29/07 | 11/13/08 | |
| EPS Software | 10.00 | 1/10/08 | 1/23/08 | |
| SMS Software | 7.00 | 12/11/07 | 12/19/07 | |
| ACS Software | 22.00 | 11/29/07 | 12/28/07 | |
| VISIM Software | 11.00 | 9/1/08 | 9/15/08 | |
| C&DH Software | 117.00 | 11/29/07 | 5/9/08 | |
| IDT Software | 10.00 | 11/29/07 | 12/12/07 | |
| Ground Station Software | 68.00 | 2/11/08 | 5/14/08 | |
| Ground Processing Software | 49.00 | 9/8/08 | 11/13/08 | |
| CDH_Sched.fts | 97.00 | 12/6/07 | 4/18/08 | |
| Processor Board Software | 17.00 | 12/10/07 | 1/1/08 | |
| Mass Storage, A/D | 25.00 | 1/2/08 | 2/5/08 | |
| Power/Modem | 44.00 | 12/17/07 | 2/14/08 | |
| Flight CFTP Board | 5.00 | 12/17/07 | 12/21/07 | |
| GPS Interface | 4.00 | 12/19/07 | 12/24/07 | |
| RF System | 86.00 | 12/6/07 | 4/3/08 | |
| Integrate C&DH Box | 10.00 | 3/5/08 | 3/18/08 | |
| Conformal coat | 10.00 | 2/15/08 | 2/28/08 | |
| C&DH Standalone EMI/EMC | 10.00 | 3/19/08 | 4/1/08 | |
| SV Coaxial cabling design | 11.00 | 4/4/08 | 4/18/08 | |
| GroundStation.fts | 239.00 | 4/10/07 | 3/7/08 | |
| Ground Station RF Hardware | 237.00 | 4/10/07 | 3/5/08 | |
| Ground Station Software | 10.00 | 2/11/08 | 2/22/08 | |
| End-to-End test | 10.00 | 2/25/08 | 3/7/08 | |
| StrucMech.fts | 227.00 | 12/5/07 | 10/16/08 | |
| Flight Structure Final Mods | 78.00 | 12/5/07 | 3/21/08 | |
| Support / GSE Parts | 227.00 | 12/5/07 | 10/16/08 | |
| Mechanical Component Test | 20.00 | 1/2/08 | 1/29/08 |